Product Has Multiple Formulas/Recipes, but One Does Not Show Up as Alternate BOM (Doc ID 2172248.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Process Manufacturing Process Planning - Version 12.2.4 and later
Information in this document applies to any platform.

Goal

For a product, one of the formulas/recipes is not showing up as an alternate BOM. It turns out that all of the ingredients in the formula are marked as Not Planned, but customer wants the formula/recipe to be collected and show up as an alternate BOM anyway.
 

Solution