On : 12.2.5 version, Other Planning Issues

ACTUAL BEHAVIOR
---------------
ECC detailed scheduling ASCP-OPM plan doesn't use alternate resources

EXPECTED BEHAVIOR
-----------------------
Acceptable Result is using all available alternative sources to generate planned orders with necessary lead times.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1) Run ASCP-OPM plan with ECC with detailed scheduling Constrained Mode.

Advanced Supply Chain Planner
(N) Advanced Supply Chain Planner>Supply Chain Plan>Names
(B) Launch Plan

2) Analyze plan details
(N) Advanced Supply Chain Planner>Supply Chain Plan>Workbench
View by Organizations


Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms