My Oracle Support Banner

ALTERNATE RESOURCE NOT USED IN ECC PLAN (Doc ID 2172556.1)

Last updated on JUNE 12, 2018

Applies to:

Oracle Process Manufacturing Process Planning - Version 12.2.5 and later
Information in this document applies to any platform.

Symptoms

On : 12.2.5 version, Other Planning Issues

ACTUAL BEHAVIOR
---------------
ECC detailed scheduling ASCP-OPM plan doesn't use alternate resources

EXPECTED BEHAVIOR
-----------------------
Acceptable Result is using all available alternative sources to generate planned orders with necessary lead times.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1) Run ASCP-OPM plan with ECC with detailed scheduling Constrained Mode.

Advanced Supply Chain Planner
(N) Advanced Supply Chain Planner>Supply Chain Plan>Names
(B) Launch Plan

2) Analyze plan details
(N) Advanced Supply Chain Planner>Supply Chain Plan>Workbench
View by Organizations


Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.