Symptoms
On : 12.1.3 version, Purchasing Processes
ACTUAL BEHAVIOR
---------------
Insert PDOI interface sourced with requisition, populate line interface need_by_date as the source requisition line need_by_date, however, the imported SPO with the different need_by_date, the issue only occurred for big batch import, if less interface records import, no issue.
EXPECTED BEHAVIOR
-----------------------
Need_by_Date of imported SPO can derived correctly from PDOI interface
STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1.Insert PDOI interface sourced with requisition, populate line interface need_by_date as the source requisition line need_by_date,
Cause
To view full details, sign in with your My Oracle Support account. |
|