Reducing Capacity for the First Hour in a Shift Makes Resource Workbench to Display Available Quantity with Wrong Values (Doc ID 2174373.1)

Last updated on OCTOBER 31, 2016

Applies to:

Oracle Work in Process - Version 12.1.3 to 12.1.3.4 [Release 12.1]
Information in this document applies to any platform.

Symptoms

On :  12.1.3 version, Workbenches

When reducing capacity from first hour of each shift, the available display of resource (blue bucket in the workbench) is showing double values

Expect to see proper data

The issue can be reproduced at will with the following steps:
1. reduce capacity for the first hour from shift
2. observe resource availability display

Cause