R12: Unable to Add tasks to Either the Work Break Down Structure or the Financial Break Down Structure as the Task Buttons don't Exist in the Project Super User Responsibility. (Doc ID 2175622.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Project Planning and Control - Version 12.2.4 and later
Information in this document applies to any platform.

Symptoms

Unable to add tasks to a newly created project template in the self service application as the create task buttons ('Delete', 'Outdent' 'Indent') do not show.  The PA:  Cross project Update and View are set to YES and the SEEDED Project Super User responsibility is being used. 

Cause