Unable To Update Operation To Complete Using WIP Mass Load (Doc ID 2177333.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Work in Process - Version 12.2.4 and later
Information in this document applies to any platform.

Goal

We are using an external MES. When operations complete within a job in MES, we want to use WIP Mass Load(WML) to interface that status back to MRP. I am able to do this at a job level, and complete the job. I cannot get the operation to complete via WML. It updates the operation (Count Point goes from checked to unchecked), but the In Queue does not move to Complete and the next operation does not go to started.

Need to know how to populate WIP_JOB_DTLS_INTERFACE and WIP_JOB_SCHEDULE_INTERFACE to accomplish this
 

Solution

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms