Actual Cost Process Performance Issue (Doc ID 2187148.1)

Last updated on JULY 07, 2017

Applies to:

Oracle Process Manufacturing Financials - Version 12.1.3 and later
Information in this document applies to any platform.
Actual Cost Process performance issue

Symptoms

On : 12.1.3 version,  Actual cost process

ACTUAL BEHAVIOR
---------------
Actual cost process normally takes 15 minutes to complete. Currently, actual cost process takes  2 days to complete.

EXPECTED BEHAVIOR
-----------------------
Better performance and for process to complete in a reasonable amount of time.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Navigation: OPM Financials>Actual cost process
 

Cause