Symptoms

On : 12.2.4 version, Invoices

ACTUAL BEHAVIOR
---------------
Invoice generation unprocessed expenditure items

I have unexpected items on the report for the PRC: Generate Draft Invoices for a Single Project. The expenditures generated successfully for revenue (final accounted with no errors). I've verified that the expenditure item date is prior to the bill thru date and the item is not on billing hold. The only unique characteristic I can determine right now is that these were entered as accruals that will reverse in the following period.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1) Run PRC: Generate Draft Invoices for a Single Project

BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, users are unable to generate expected invoice amount for SIT testing to progress

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.