Preventive Maintenance Schedule Date Are Inaccurate

(Doc ID 2192581.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Enterprise Asset Management - Version 12.1.3 to 12.2.6 [Release 12.1 to 12.2]
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR
For asset JO732661, the next Work Order (WO) Due Date is shown as Aug 2, 2016 although interval days is 365 days and the last WO is 5/5/2016 .

EXPECTED BEHAVIOR
For asset JO732661, the next Work Order (WO) Due Date should be around 5/5/2017

STEPS

The issue can be reproduced at will with the following steps:
1. Choose an Asset Group
    Asset no 
    Activity
   Set Name
   Schedule Name


2.  Responsibility = Enterprise Asset Management (EAM)
    Navigation = Preventive Maintenance-> Generate Work Orders
 
3. Responsibility = Maintenance Super User
  Navigation = Work Orders-> Work Orders
  Work Order is created with an illogical start date.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms