Requisition Import Get Error GL Date is not in a Valid Period (Doc ID 2194382.1)

Last updated on OCTOBER 18, 2016

Applies to:

Oracle Purchasing - Version 12.2.5 and later
Information in this document applies to any platform.

Symptoms

When running Requisition Import  get error GL date is not in a valid period


Cause: GL date must be in a valid period if encumbrance is ON

Inventory, Purchasing, and General Ledger periods are open

Profile Option "PO:Validate GL Period" is set to "Redefault"