Costs View Of The Oracle EAM Work Order Doesn't Show Correct Updates Due To PR Change Request (Doc ID 2197156.1)

Last updated on OCTOBER 26, 2016

Applies to:

Oracle Enterprise Asset Management - Version 12.1.3 and later
Information in this document applies to any platform.

Goal

When trying to update a price for purchase requisition amount in the iProcurement Requisitions tab, the updated PR amount did not
get updated to the EAM Cost distribution window for the given work order.

The expected behavior is the amount should be updated to the cost distribution form once the price is updated.
 