The Maintenance Workbench Is Not Transferring Costs To Projects (Doc ID 2202696.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Work in Process - Version 12.1.3 to 12.1.3 [Release 12.1]
Information in this document applies to any platform.

Symptoms

On :  12.1.3 version, Discrete & Flow Workstation

ACTUAL BEHAVIOR  

Jobs completed via the Discrete Workbench do not reduce the project cost group component quantities on the inventory material workbench.  Whereas, the Move transaction form correctly reduces cost group quantities in the material workbench.

EXPECTED BEHAVIOR

Discrete workbench Inventory transactions to function identically to move transactions

Cause