EAM: PM Forecast Is Not Responding To Actual End Date Scheduling Option On PM Schedule
(Doc ID 2203283.1)
Last updated on JULY 18, 2024
Applies to:
Oracle Enterprise Asset Management - Version 12.1.3 and laterInformation in this document applies to any platform.
Symptoms
ACTUAL BEHAVIOR
The PM Forecast is incorrectly forecasting dates for a PM Schedule. The PM Schedule is
configured to use the Actual End Date to suggest next service start date,
however irrespective of what date is used here the PM Forecast continues to generate WO for a different date.
EXPECTED BEHAVIOR
Expect to see the correct forecast when scheduling option is set to Actual End Date.
STEPS
The issue can be reproduced at will with the following steps:
1. Responsibility: Enterprise Asset Management.
2. Go to Maintenance Workbench.
3. Query asset.
4. Go to Forecast Work Orders screen and enter required data.
5. Incorrect suggestions created by PM engine.
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Cause |
Solution |