WIP Mass Load Is Not Updating Supply Subinv/locator On Open Requirements On A Job In Released Status

(Doc ID 2205053.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Work in Process - Version 12.1.3 and later
Information in this document applies to any platform.


On : 12.1.3 version, Open Interfaces

When the WIP Supply subinventory/locator is updated on an item and the WIP Mass Load program is executed, the supply subinv/locator for that item on any Released jobs where that item has an open requirement is NOT updated.

WIP MASS LOAD should update the supply subinventory updated in Organization Items screen.

The issue can be reproduced at will with the following steps:
1. Responsibility: Work in Process
2. Discrete - > Discrete
3. Create a Discrete Job
4. Responsibility: Inventory
5. Items - > Organization Items
6. Tab down to Inventory
7. Change the supply subinventory.
8. Switch to Work in Process
9. Launch the WIP MASS LOAD request.
10. Check the supply Subinventory in Material requirements form.
11. Supply subinventory is not updated.


Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms