Auto Create Configuration of Star Item Does Not Consider Disable Date for Resources In Model Item Routing (Doc ID 2207788.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Configure to Order - Version 12.1.2 and later
Information in this document applies to any platform.

Symptoms

OBSERVED BEHAVIOR

User has identified the following issue with Star item(Routing):
While creating * item routing, system is not considering the "disable date" for one resource (scheduled resource) in Model item routing. Please suggest solution for this issue

EXPECTED BEHAVIOR

The Star item should consider the disable date for one of the resources

STEPS TO REPRODUCE

1. Model item routing created (in November 2014)
2. Model item routing updated through ECO (in August 2015) - deleted 4 days scheduled resource from Operation 10, added operation 9998 with 4 days scheduled resource (so lead time remains the same) - Please note that Operation 10 has other resource, which has Schedule = No and it is not altered.
3. Sales Order for Model created, booked and progressed the order to create * item and WIP Job
The * item routing has 2 scheduled resources (one in operation 10 and other in operation 9998), therefore lead time for * item routing and WIP Job is 8 days
Results:
The application is not considering disable date for one of the resources while creating the *Item.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms