DFF 'component Information' Shows Different Values For Components In BOm And In WIP Job

(Doc ID 2208140.1)

Last updated on DECEMBER 19, 2016

Applies to:

Oracle Work in Process - Version 12.2.6 and later
Information in this document applies to any platform.


The information in the Bill of Materials doesn't match up with the information in the WIP Discrete Job Material Requirements page.

Expect information to be consistent.

The issue can be reproduced at will with the following steps:
1. Responsibility: Work In Process
2. Navigation: Bill tab > Material Requirements > Component information - BOM Quantity shows nothing
3. Responsibility: Bill O f Materials > Bills > Bills > Component Information - shows BOM Quantity as 1.


Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms