My Oracle Support Banner

Close Discrete Jobs Fails With Project Is Currently Not Chargeable (Doc ID 2210219.1)

Last updated on FEBRUARY 03, 2019

Applies to:

Oracle Work in Process - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

When attempting to close project related discrete jobs, the following error occurs.
The issue does happen for both the close discrete jobs (Form) and the close discrete jobs (SRS) process. The project is in Approved status so it is chargeable.


ERROR

The specified project (xxxxxx) is currently not chargeable. Please enter another.


STEPS

The issue can be reproduced at will with the following steps:
1. Responsibility: Work In Process
2. Navigation: Discrete -> Close Discrete Jobs -> Close Discrete Jobs(SRS)
3. Parameters:
  Status – Complete – No Charges
  Exclude Reserved Jobs – Yes
  Exclude Un-Completed Jobs – Yes
  Exclude Jobs with Pending Transactions – No
  Report Type – Summary
  Actual Close Date – Date process is ran
4. Click OK
5. Click Submit

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.