Changing PM Schedule Rule From Scheduled Start Date To Base Date having open work orders for same PM

(Doc ID 2218015.1)

Last updated on JANUARY 20, 2017

Applies to:

Oracle Enterprise Asset Management - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

On : 12.1.3 version, PM

ACTUAL BEHAVIOR

Changing the Rule from Scheduled Start date to base date is allowed when there are open work orders for same PM schedule



EXPECTED BEHAVIOR

Changing the Rule from Scheduled Start date to base date should not be allowed when there are open work orders, error message should be triggered

 


The issue can be reproduced at will with the following steps:

1. In the Existing PM schedule Change the rule to Base date while there are open work orders

2. Run the PM Schedule .

3. Forecast orders are not in correct sequence .



Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms