R12 Working Change Requests do not Appear in the 'View Included Change Documents' Drop Down Menu. (Doc ID 2219597.1)

Last updated on FEBRUARY 20, 2017

Applies to:

Oracle Project Planning and Control - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

Working change requests do not appear in the financial plan when viewing the change documents using the 'View Included Change Documents' drop down on either the Working or Approved version of the forecast. A working change order appears in the view, but not the change request. Both a primary and non primary forecast plan type was used based upon the documentation and the change request did not appear in either:

Oracle® Project Management
User Guide
Release 12.1
Part No. E13623-05

You can only include the financial impact of approved change orders in plan
versions designated as approved cost budgets or approved revenue budgets.
¿ You can include the financial impact of a change order or change request of
any status in plan versions (including forecasts) that are not approved cost
or revenue budgets.

Steps to reproduce:

1. Create both a change order and change request in Working status.
2. Add a forecast plan type (with both the change order and change request type added to the plan type) to the project and from either the Working or Approved version of the forecast, select 'View Included Change Documents' from the drop down.

The change order is viewable, but not the change request.



Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms