R12 Implemented Change Order Shows Twice Overstating the Projected Total in 'View Included Change Documents' View. (Doc ID 2219607.1)

Last updated on FEBRUARY 20, 2017

Applies to:

Oracle Project Planning and Control - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

Projected Total in the 'View Included Change Documents' from budget version drop down page is overstated.

When a change order is implemented, it appears in both in the row 'Change Documents Included in this Version' and in the row 'Approved Change Documents' resulting in the 'Projected Total' being overstated by the amount of the Change order. For example:

Current Baseline 1500
Change Doc Included 700
Total Current Working 2200 <==this is correct
Approved Change Docs 700
Projected Total 2900 <==this is overstated by the amt of the CO



Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms