Symptoms

ACTUAL BEHAVIOR
---------------
When planning orders onto ground scheduled shipments, the ERU equipment capacity is not taken into consideration during planning as more capacity is planned on to the equipment than should be allowed.

EXPECTED BEHAVIOR
-----------------------
It is expected that the shipment be planned with an equipment group that holds the respective amount of ship units based on the equipment capacity defined for the ERU and to not exceed that limit.

STEPS
-----------------------
1. Navigate to Order Management -> Order Release -> Order Release
2. Search for order an order to be planned with a quantity known to exceed the capacity of the equipment the order is to be planned on.
3. Plan this order using a parameter set that will allow for OTM to check equipment capacity based on ERUs (Note: Set parameter CHECK EQUIPMENT CAPACITY IN REFERENCE UNITS to TRUE to allow calculating equipment capacity in ERUs).  Ensure the order is planned onto a previously generated ground schedule shipment
4. The shipment planned for this order has a quantity that exceeds the equipment ERU capacity.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms