R12: PAAPIMPB Invoices Error with '"The item date is not within the project active dates" as the Expenditure Item Date Fall Outside of the Project Dates. (Doc ID 2225267.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Project Costing - Version 12.2.4 and later
Information in this document applies to any platform.

Symptoms

When running the PRC: Interface Supplier Cost process, tax related lines and tax rate exchange variances give "The item date is not within the project
active dates" in the output. When looking at the data, the tax and TRV lines PRE-date the PO/invoice/project.

Cause