My Oracle Support Banner

R12: While Sending Project Data From Microsoft Projects (MSP), Scheduling Attribute Values Are Not Sent to Oracle Projects (OP) (Doc ID 2233086.1)

Last updated on APRIL 17, 2017

Applies to:

Oracle Project Planning and Control - Version 12.2.5 and later
Information in this document applies to any platform.

Symptoms

While sending project data from Microsoft Projects,  below scheduling attribute values are not sent to Oracle Projects:


  Constraint Type
  Constraint Date
  Free Slack
  Total Slack
  Type
  Scheduled Duration
  Actual Duration
  Remaining Duration
  Effort Driven
  Level Assignments

Reproducible Steps
------------------

1. Install MSP integration

2. Create a new task in MSP

3. Give some values for below scheduling attributes:

Constraint Type
Constraint Date
Free Slack
Total Slack
Type
Scheduled Duration
Actual Duration
Remaining Duration
Effort Driven
Level Assignments

4. Create a new project from MSP (with the above task and scheduling attributes) using Cost Plus Template

5. Login to the application, search for the project

6. Click on project number/name and go to Workplan -> Update Tasks page

7. Click on Update pencil icon against the task

8. Go to Schedule Tab

9. In the bottom, expand Options to see Scheduling attributes. See that the above scheduling attribute values are not sent from MSP to Oracle Projects.

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.