Error API GME_API_PUB.complete_step 'Actual start date 29-XXX-2016 00:55:18 of step 10 cannot be earlier than the actual complete date of previous step (Doc ID 2240745.1)

Last updated on MARCH 09, 2017

Applies to:

Oracle MES for Process Manufacturing - Version 12.2.4 and later
Information in this document applies to any platform.

Symptoms

On : 12.2.4 version, MES/Dispensing

When attempting to complete Batch step using the API GME_API_PUB.complete_step API
the following error occurs.

ERROR
-----------------------
Actual start date 29-DEC-2016 00:55:18 of step 10 cannot be earlier than the actual complete date 29-DEC-2016 01:38:46 of previous step


STEPS
-----------------------
The issue can be reproduced at will with the following steps:

1. Complete the Step using API.


Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started