Symptoms

On : 12.2.6 version, Inbound Processing

Putaway Drop failed to Crossdock to WIP Job,
the following error occurs.

ERROR
-----------------------
Ex.. in processTrxBatch ..:java.sql.SQLException: Closed Resultset: NEXT

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
STEPS
-----------------------
The issue can be reproduced at will with the following steps:
WMS responsibility>
Define Crossdock Criteria:
GE UMEA Cross Docking
Planning tab:
Opportunistic Crossdocking
Schedule Demand any time on Shipment date
Integer Quantities Only
Demand tab:
Demand type: WIP Component Demand (Backordered)

Manufacturing resp>
Discrete Jobs>Released> Material Requirement>Supply type: Push
Component Pick Release> Check Supply/Demand

WMS responsibility>
Inbound Logistics>Receipts
Packing Initialization>LPN Pack>Generate LPN

Oracle Mobile responsibility
Receive>PO>Receipt>Receipt Information>Done
Receive>Internal Req >Tasks>Manual Tasks>Move Any LPN>Move LPN: fill the LPN
number>press Drop
Drop LPN>Transfer Contents>get message:
The task errored out while processing. Do you want to continue with the next
task?
Press Yes>get No tasks available.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms