When Closing Outside Processing (OSP) Batches In OPM Receive Error "There is no completed resource transaction for the OSP step" (Doc ID 2251540.1)

Last updated on JULY 17, 2017

Applies to:

Oracle Process Manufacturing Process Execution - Version 12.2.4 and later
Information in this document applies to any platform.

Symptoms

On : 12.2.4 version, Batches

OSP Batches in OPM
Have a scenario wherein for the OSP Batches, the PO's are already created and therefore the PO's/Reqs that are created because of OSP Step are not needed. Have cancelled such PO/Req which are created because of OSP step. Now when are trying to close these batches Getting an attached error.



ERROR
-----------------------
There is no completed resource transaction for the osp step. Please run resource manager concurrent program to import pending resource transaction in the resource transaction open interface.




STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Production Supervisor > Batch > Batch Details



Cause

Sign In with your My Oracle Support account