My Oracle Support Banner

Schedule Resource Value Shown As Yes On WIP Job When Copied from Phantom Routing in R12 (Doc ID 2254354.1)

Last updated on APRIL 12, 2017

Applies to:

Oracle Work in Process - Version 12.1.3 and later
Information in this document applies to any platform.

Goal

Comparing to 11i release, where the schedule flag from phantom routings is not inherited but always is NO, in 12.1.3, the resources are inheriting the flag from the phantom routings. Why and how can be controlled?
 

Solution

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Goal
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.