Symptoms

On : 12.2.5 version,

In the Service Request form, when attempting to create a field service task and schedule it manually, the following error occurs.

ERROR
-----------------------
Please enter a quantity for planned efforts


STEPS
-----------------------
The issue can be reproduced at will with the following steps:

1 - Create a SR
2 - Create a Task in Pending status - Planned effort UOM defaults to 8 hours, Planned start time & end time defaults to current time
3 - Manually assign the task to a resource - Works fine
4 - Enter schedule start date. Schedule end date is calculated as schedule start date + 8 hours
5 - At this point of time, the planned effort hours disappear but the effort UOM remains as "Hours".



Changes

 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms