R12: FPEDITPLANPG, ETC Forecast Calculation for COST/EVENT Incorrect (Doc ID 2257396.1)

Last updated on AUGUST 03, 2017

Applies to:

Oracle Project Planning and Control - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

Revenue Forecast is calculating at task level it is doing at project level.

Two tasks exist on the Project.  One task, only, has the Budgeted Revenue.
The Revenue Forecast, based on the Workplan resource hours, splits hours based on the project; not on Task.

Cause