Cannot Complete Receiving Due To Receipt Date - Date Entered Is Not Within The Tolerance Period
(Doc ID 2259585.1)
Last updated on AUGUST 20, 2023
Applies to:
Oracle iProcurement - Version 12.1.3 and laterInformation in this document applies to any platform.
Symptoms
On : 12.1.3 version, Receiving Functions
Cannot complete the receiving for a standard purchase order for a particular operating unit in iProcurement responsibility.
When the tolerance is changed to enter the date in the last month (March in this case), another error is shown:
The Purchasing Accounting Period in which you are trying to create this receiving transaction is not open for the following item(s). Please contact your administrator.
ERROR
-----------------------
The error shown is:
Warning:
Receipt Date - Date entered is not within the tolerance period set-up for the following items. Correct the date entered, or press the next to accept the existing date.
-Expected receipt date is 29-Mar-2017
Then, next error is:
The Purchasing Accounting Period in which you are trying to create this receiving transaction is not open for the following item(s). Please contact your administrator.
STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Enter receipt data
2. See error
3. Cannot proceed with submitting the receipt.
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Cause |
Solution |