My Oracle Support Banner

Resource Schedules Are Spontaneously Doubling Up (Doc ID 2259839.1)

Last updated on FEBRUARY 21, 2019

Applies to:

Oracle Work in Process - Version 12.2.5 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR

The resource capacity units are doubling up when making updates to the resources. It doubles from 1 unit to 2 units, and 2 units to 4 units and 4 units to 8 units.
This functionality was working fine prior to the upgrade from 11.5.10.2 to 12.2.5.


EXPECTED BEHAVIOR

Resource Schedules should not double up.


STEPS

The issue can be reproduced at will with the following example:
1. Navigate to Work in Process > Discrete> Resource Workbench
2. Current Resource Schedule
3. Delete and Add Capacity
4. Re-query the resource schedule.
5. Notice line # 2. It doubled up.


Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.