OSP Item Received But No Impact On Associated Job (Doc ID 2260107.1)

Last updated on APRIL 27, 2017

Applies to:

Oracle Work in Process - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR

Outside Processing Purchase order (OSP) was received for 10100 units. The PO shows the receipt but the corresponding work order does not show the completion for the same amount.
When receiving OSP item, the easy-completion is not done automatically (auto-completion) for the associated discrete job (i.e., Job is still in Released Status even though PO was received).


EXPECTED BEHAVIOR

The work order should show the completion for the same amount as the PO amount.


STEPS

The issue can be reproduced at will with the following steps:
1. Responsibility: Work In Process.
2. Go to Discrete Jobs -> Discrete Jobs.
3. Find job 1176808 in Status = Released, Assembly = 096N00270.
4. PO is already received.


Cause

Sign In with your My Oracle Support account