Symptoms

On : 12.2 version, Constrained planning

ACTUAL BEHAVIOR
---------------
Forecast in Horizontal Plan is not equal to the Horizontal Planning Detail Report.


EXPECTED BEHAVIOR
-----------------------
Report should show correct data

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. (R) Advanced Supply Chain Planner
2. (N)Reports/Planning Detail report
3. Enter the parameters and run the report


Cause