Inactive Resource is Available for Selection When Charging Time to Work Orders (Doc ID 2270167.1)

Last updated on MAY 25, 2017

Applies to:

Oracle Enterprise Asset Management - Version 12.1.2 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR

End dated resource still shows up in the list of values when charging time to work orders.


EXPECTED BEHAVIOR

Inactive resource should not be available for selection when charging time to work orders.


STEPS

The issue can be reproduced at will with the following steps:
1. Go to Resources form and set Inactive On.
2. Charge time on the work order, where the creation date is greater that resource code end date.
3. The Resource LOV shows inactive resource to be selected.

Cause