Item Received For LCM Enabled PO Receipts Is Higher Then Expected. (Doc ID 2270220.1)

Last updated on JUNE 04, 2017

Applies to:

Oracle Landed Cost Management - Version 12.2.4 and later
Information in this document applies to any platform.

Symptoms

On : 12.2.4 version,

Although no additional charges are entered in LCM ,item is receive at an higher cost in inventory
 
STEPS
-----------------------
The issue can be reproduced at will with the following steps:

1.Create PO > with multiple po lines
2.Approve
3.Create LCM Shipment
4.Create LCM shipment lines
5.Do not add any charges /  taxes
6.Validate/calculate /submit
Review the landed cost in Shipment workbench (for example is 25)
7.Receive the quantities in full
8.Items received at higher cost

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms