How to Make Rescheduling on the Gantt Chart Respect Individual Resource Calendars (Doc ID 2272131.1)

Last updated on MAY 31, 2017

Applies to:

Oracle Process Manufacturing Process Planning - Version 12.1.3 and later
Information in this document applies to any platform.

Goal

When a particular resource has its own calendar, while manually rescheduling in the Gantt chart, the reschedule does not respect the resource calendar, but respects the general calendar.
In result, resource capacity is not respected even if we set resource unavailability by using different calendar on resource level. Also, there is no system message that we can not schedule order at such date. There is such verification for main organization calendar only.
 

Solution