Error : FORECAST: The Time Phase Of The Change Order And Current Working Version Are Different. (Doc ID 2275551.1)

Last updated on JUNE 30, 2017

Applies to:

Oracle Project Planning and Control - Version 12.1.3.1 and later
Information in this document applies to any platform.

Symptoms

On : 12.1.3.1 version, Change Management

When using FORECAST for a change order, get the following error:

Error : FORECAST: the time phase of the change order and current working version are different. The time phase must be the same in order to implement the financial impact of the change order in the plan version

 As a result the change order cannot be implemented.

Cause

Sign In with your My Oracle Support account