R12 AP: Create Netting Batch Taking 5 Days To Complete If Netting Agreement Parameter Is Not Entered (Doc ID 2278975.1)

Last updated on JUNE 21, 2017

Applies to:

Oracle Payables - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms


Performance issue - Create Netting batch

Create Netting Batch program completes in 6-7 days
when user has not selected any netting agreements
but selected all other required dates criteria
(settlement Date, Transaction due date & GL Date).

- If Create Netting Batch program is run by providing a NETTING AGREEMENT,
the job completes within a minute. So, this scenario is not a problem.

- However, if Create Netting Batch program is run without choosing a NETTING AGREEMENT,
the job runs for days (almost a week).

 

 

 

 

 

 

Cause