After Patch 21222032:R12.GMF.B Different Lot Cost for Two Product Lots Yield from Same Batch (work Order) at Same Time (Doc ID 2280674.1)

Last updated on JUNE 26, 2017

Applies to:

Oracle Process Manufacturing Financials - Version 12.0.0 and later
Information in this document applies to any platform.

Symptoms

After running Lot Cost Process

Actual Behavior

Different lot cost to the two product lots yield from same batch at the same time

Expected Behavior

Same lot cost to the two product lots yield from same batch at the same time

Reproducible Steps

1. Apply Patch 21222032:R12.GMF.B

2. Yield two product lots for the same batch (including multiple resources) at the same time

3. Run Lot Cost Process, found the issue.

Cause

Sign In with your My Oracle Support account