Jobs Are Created And Released Earlier/prior Wrt Schedule Ship Date Of Sales Order. (Doc ID 2281327.1)

Last updated on JUNE 28, 2017

Applies to:

Oracle Work in Process - Version 11.5.10.2 to 12.2.6 [Release 11.5 to 12.2]
Information in this document applies to any platform.

Goal

The job is created and released prior to the schedule ship date of the Sales order.
job creation date - 21-FEB-2017 02:13:25
SO schedule ship date - 07-03-2017 23:59:00
Cumulative manuf leadtime - 3
Cumulative Total leadtime - 13
lot size -1
offset days - 5 days

We want to know after considering all this factors how does a job gets release prior to the time frame.
Why Jobs are created and released earlier/prior wrt schedule ship date of sales order?
Please let us know the calculations based on the WIP details i have given, We want the concrete calculations which are been done by the system to arise at the said date. And as per the offset days functionality , the job creation date is not correct, which business wants to understand. This is impacting lot many jobs everyday so please expedite on the same.
 

Solution

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms