How System Calculate Preventive Maintenance Schedule date ? (Doc ID 2284704.1)

Last updated on JULY 18, 2017

Applies to:

Oracle Enterprise Asset Management - Version 12.2.3 and later
Information in this document applies to any platform.

Goal

On : 12.2.3 version, PM

The Preventive Maintenance generate wrong date

Why the system suggest 23-08-2017 08:00:00?

 The formula is (Last service reading + Base interval)/Usage rate= (0+2000)/24= 83.33333 days´âĘthe suggest date is 26-SEP-2017.
 

Solution