You May Not Modify Payment Dates That Are Prior To The Rebook Effective Date. (Doc ID 2284798.1)

Last updated on JULY 10, 2017

Applies to:

Oracle Lease and Finance Management - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

On : 12.1.3 version, Lease Authoring

You may not modify payment dates that are prior to the rebook effective date.

While Testing Rebook in UAT instance the system is not allowing me to input the Rebook date as sys date or any other date after the contract start date , If I do so and try to update the payment line ( Cancellation of Service line by making the future payments as zero) I get a error message "You may not modify payment dates that are prior to the rebook effective date."

If I give contract start date as Rebook date the system is allowing me to update the payments, and after billing program is run I do not see credit memos generating from the contract start date.

Suppose the contract is billed for 6 months out of 12 and through rebook if I update the payment as 4months x 10 & 8months x 0 and run billing then 2 credit memos are generated.

If  update the payment as 6months x 10 & 6months x0 and run billing no credit memo is generating.

 

ERROR
-----------------------

"You may not modify payment dates that are prior to the rebook effective date."




STEPS
-----------------------
The issue cannot be reproduced at will with the following steps:



Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms