Goal

There are three “ComponentA” in “ItemA” BOM. The Quantity and Supply Type are as follows. When job is created for ItemA, requirement row is merged into single row with supply type:push. Is it intended behavior?

Example:
ItemA
-PhantomA -----  Quantity:1--Supply Type:Phantom
--ComponentA -- Quantity:1--Supply Type:Push
-PhantomB -----  Quantity:1--Supply Type:Phantom
--ComponentA -- Quantity:1--Supply Type:Push
-ComponentA ----Quantity:1--Supply Type:Assembly Pull

Solution