PDS Award Modifications Not Displaying Correct Changed Amount For Modification Headers (Doc ID 2287235.1)

Last updated on JULY 21, 2017

Applies to:

Oracle Contract Lifecycle Management for Public Sector - Version 12.2.3 and later
Information in this document applies to any platform.

Symptoms

In CLM, the modification change amount on the CLM award modification is not reflecting the correct amount

Steps to Reproduce :
------------------------
1. Login to the E-Business Suite and select the CLM responsibility
2. Navigate to AWARDS-MODIFICAITONS and query a modification.
3. Notice that the changed amount is wrong

Cause