PAXPREPR Not Validating Expenditures At Project Level (Doc ID 2288279.1)

Last updated on JULY 19, 2017

Applies to:

Oracle Project Planning and Control - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

In PAXPREPR, the project transaction start date/end date is not working as expected.

The application allows users to change the project completion date to a date earlier than the expenditure item date of existing transactions for the project.

Also, the application allows users to change the project start date to a date later than the expenditure item date of existing transactions for the project.

Cause