Symptoms


ACTUAL BEHAVIOR

The Operation Properties region in MES wrongly considers returned, scrapped or rejected quantities as completed.

For example, if a Job Op has a quantity of 50, 30 out of which are completed and 20 scrapped, it shows all 50 as completed.

Similarly if, after completing all 50, 20 are returned to the operation, it still shows all 50 as completed.


EXPECTED BEHAVIOR

MES should consider returned, scrapped or rejected quantities as completed.