R12: Forecast Change Documents Included In This Version Display (Cost = 0 and Revenue = 0) (Doc ID 2290068.1)

Last updated on JULY 25, 2017

Applies to:

Oracle Project Planning and Control - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

Users are implementing Change Control functionality.  In the section Summary plan, the change document from prior
baseline versions is null and its added to the adjustment from prior baseline versions amount.


Change documents included in this Version show (cost = 0; revenue = 0) for the forecast version.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:

- After implementing the change order financial impact in budget and forecast (cost = 2024.56; revenue = 4010.12)
- Go to the Financial tab and select budget and displays the current version (with View included change document). The Change Documents Included in this Version display (cost = 2024.56 and revenue = 4010.12)
- When the user does the same thing with forecast the section Change Documents Included in This Version display (cost = 0; revenue = 0)

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms