Symptoms
Users are implementing Change Control functionality. In the section Summary plan, the change document from prior
baseline versions is null and its added to the adjustment from prior baseline versions amount.
Change documents included in this Version show (cost = 0; revenue = 0) for the forecast version.
STEPS
-----------------------
The issue can be reproduced at will with the following steps:
- After implementing the change order financial impact in budget and forecast (cost = 2024.56; revenue = 4010.12)
- Go to the Financial tab and select budget and displays the current version (with View included change document). The Change Documents Included in this Version display (cost = 2024.56 and revenue = 4010.12)
- When the user does the same thing with forecast the section Change Documents Included in This Version display (cost = 0; revenue = 0)
Changes
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Changes |
Cause |
Solution |
References |