Discrete Job Is Not Getting Scheduled After Upgrade.

(Doc ID 2294387.1)

Last updated on SEPTEMBER 02, 2017

Applies to:

Oracle Work in Process - Version 12.2.6 and later
Information in this document applies to any platform.

Symptoms

On : 12.2.6 version, Work Order Definition

ACTUAL BEHAVIOR
---------------
When a new Job is created the completion date is not calculated based on the lead time..
because of that the completion date is always same as the Start Date

EXPECTED BEHAVIOR
-----------------------
Expect to see the Completion date calculated based on the Assembly item lead time..

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Wip-->Discrete-->Discrete jobs
2. Enter the Assembly, Quantity and Start Date-->Save
3. Observe that the Completion date is calculated to be same as the start date..
4. The lead time is not taken to consideration

 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms