Batch Steps Appear to Be Planned for Too Many Days, Duration is Longer Than Expected (Doc ID 2299313.1)

Last updated on AUGUST 21, 2017

Applies to:

Oracle Process Manufacturing Process Execution - Version 12.2.5 and later
Information in this document applies to any platform.

Symptoms

On : 12.2.5 version, Batches

ACTUAL BEHAVIOR
---------------
Batches and batch steps seem to be created with an incorrect duration, they run for too many days.

The routing header qty is 250 KG and all three steps have a step qty of 250 KG.

The resource in step 10 processes 250 KG in 720 hours, which is exactly 30 days.
The longest duration resource in step 20 processes 250 KG in 1440 hours, 60 days.
The longest duration resource in step 30 processes 250 KG in 2880 hours, 120 days.

Batch was created for 250 KG of product.
So it is expected that the steps will have the following durations:
Step 10 720 hours
Step 20 1440 hours
Step 30 2880 hours

However, the durations of the steps and those resources appears to actually be:
Step 10 30.5 days
Step 20 61 days
Step 30 122 days

EXPECTED BEHAVIOR
-----------------------
Expect the duration of each step to be as expected

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms