OPM Make To Order 'GMEMTO' Batch Is Not Getting Created 'Zero order line rows to process'

(Doc ID 2301359.1)

Last updated on AUGUST 27, 2017

Applies to:

Oracle Process Manufacturing Process Execution - Version 12.2.6 and later
Information in this document applies to any platform.

Symptoms

On : 12.2.6 version, Other Issues

ACTUAL BEHAVIOR
---------------
The MTO Concurrent program is not generating any Batches .

EXPECTED BEHAVIOR
-----------------------
The MTO Concurrent program need to create batches based on the rules .

STEPS
-----------------------
The issue can be reproduced at will with the following steps:

1. MTO rule was created for Item type finished good , Customer name XXXX.

2. Item XXXX item is Invetory item , OE Transactable and Process Execution enabled .

3. When the Concurrent program is run no batches are created .



Cause